logo
 
dre

PROJECTS

TEST
 
FLAT ROCK DREDGE, TRINIDAD
  TEST PILING, TRINIDAD

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Taylor Woodrow “Flotech”, Dominican Republic 1987 - 1988 Resident Manager/ Marine Superintendent
Twin 8” diameter pipe line installation for Shell Refindonsa.  Underwater blasting, air lifting, clamshell dredging, one mile pipeline controlled pull.  Installation of four point mooring system with four 18 ton steel anchor blocks 20 feet below sea bed.

The Moorings Limited, Grenada, W.I.
1989 - 1990 Resident Manager/ Marine Superintendent
Secret Harbour Marine Projects A & B.  A – Steel and wooden dock construction.  B – Pre-cast concrete dock construction.  All steel and concrete pile driving, land reclamation, pre-cast and insitu concrete works.

Grenada Ports Authority, Grenada, W.I.

Wreck removal project.  Salvage of 200 foot ship.  Underwater cutting, airlifting and diving. 

Grenada Ports Authority, Grenada, W.I.

Carriacou Dock Rehabilitation Project.  Repairs to main dock, pile driving, installation of harbour marker piles and pile extraction. 

Trinidad & Tobago Ports Authority, Port of Spain Harbour, Trinidad, W.I.
1990 - 1991 Resident Manager/ Marine Superintendent
Rehabilitation Project, replacement of Harbour marker lights, design and installation of pile cluster.

Omai Gold Mines, Linden, Guyana
1990 - 1991 Resident Manager/ Marine Superintendent
Green heart dock construction, Pile driving and dredging.

Reynolds Bauxite, Demerara River, Guyana

Four point Mooring System. 

George Wimpy International
Tobago
1991 - 1992 Resident Manager/ Marine Superintendent
Deep Water Harbour Project and new cruise ship dock construction, Scarborough, Tobago, W.I.  Including, Reef rock removal and dredging.            

Courland Bay Marine Project,  Tobago 1991 - 1992 Resident Manager/ Marine Superintendent
Steel and Pre-cast concrete dock construction.  Including, pile fabrication and pile driving.

Ports Development Project, Contract B, Tortola and Virgin Gorda, BVI. 
1992 - 1993 Resident Manager/ Marine Superintendent
New Cruise Ship Dock Construction and port rehabilitation.  Including dredging, land reclamation, tubular and sheet pile driving, rock drilling, reef removal, pile fabrication and testing. 

Guymines Limited, Guyana
1994 Project Manager
Rehabilitation of Bucyrus Erye 2000 ton dragline crane.  Including, sandblasting, priming and painting of dragline unit inside and out and the 400 ft. boom.  Complete refitting of electric motors, wiring, gears and bearing set.

St. Kitts Government, City Expansion Project, Marina and Cruise Ship Facility
1994 - 1998 Marine Superintendent
Dredging and reclamation of 25 acres (1,000,000 cu.yds. of material).   Installation of 5,000ft. of sheet piles, concrete bulkheads and construction of a sixty berth marina.  Installation of green heart piles, wooden dock construction and installation of tubular piles for a 2,500 foot cruise ship dock.  All prefab and insitu concrete work, sea defense armor rock placement and salvage operation.

St. Kitts & Nevis Government – Cruise Ship Dock Rehabilitation Project
1994 - 2003 Marine Superintendent/ Offshore Manager
Demolition of damaged cruise ship dock, extraction of tubular piles and dredging of berthing faces using 20” Cutler Suction Dredge, in preparation for the construction of Contract 5, which included:

Installation of 34” diameter tubular piles, temporary works and formwork for insitu concrete in beams, caps, deck topping and dolphin structures.

Derocher Dock and Dredge,
Nevis
1994 - 2003
Revetment placement and installation of breakwater at the Four Seasons Hotel, Nevis.           

St. Kitts & Nevis Ports Authority
1994 - 2003
Dock repair, dolphin structure installation and dredging.    

St. Bartholomew’ s Hotel Society 1994 - 2003
Coastal erosion repair, dredging and beach replenishment.          

St. Martin Ports Authority
1994 - 2003
Dredging and land reclamation.                

Port De Pleasance, Simpson Bay, St. Martin
1994 - 2003
Dredging of rock and clay for the Port de Pleasance Marina.        

The Urban Development Corporation, St. Kitts & Nevis
1994 - 2003
Design and Construction of new dock and marina reconstruction project. 

Atlantic LNG / Bechtel International Train 4 Jetty 2 Trinidad 2003 - 2005 Marine Consultant/ Offshore Manager
Construction of a 700 meter pre cast concrete jetty for the berthing of  LNG tankers.
Installation of 325 -18”, 20” and 16” dia Octagonal concrete piles up 24 tons each.
Installation of 122 - 36” dia  steel piles 140 ft long
Installation of  4 breasting and 6 mooring Dolphins

Trinidad and Tobago Coast Guard / Ministry of National Security 2003 - 2005 Marine Consultant/ Offshore Manager
Construction of 600 foot concrete birthing arm jetty
Installation of 45- 24” dia concrete piles and 90- 34” dia steel piles.

Jamaica Energy and Power 2005 Marine Consultant/ Offshore Manager
Construction of berthing face and underwater cofferdam for securing their 200 foot floating electric plant. Dredging of Basin.
600 foot of sheet piling with tie rods and anchor piles
300 foot concrete bulkhead

World Wide Equipment Caribbean Ltd   Claxton Bay,Trinidad 2006 Marine Consultant/ Contractor
Installation of 300 foot sheet pile bulkhead with anchor piles and tie rods
Installation of 10 No 36” dia tubular piles and 72- 16” dia concrete piles
Dredging and concrete work.

Ministry Of Works Trinidad Government 2006 - 2007 Marine Consultant/ Construction Manager/ Construction Supervisor
Preliminary design, budget estimates, pre- qualification and tender documents, geotechnical investigations, bathymetric surveying, pile driving analyzer dynamic pile testing, tubular pile driving, dredging, breakwaters, costal protection, pre-stressed concrete dock construction for the installation of 6 ferry terminals for the Trinidad and Tobago Water Taxi Service. Supervision of dredging and disposal of 245,000m3 of spoil, pile-preparation and piling at Flat Rock San Fernando.

Delta Logistics Ltd, Carricou 2008 - 2009 Contractor
Straightening and sealing 200ft concrete sheet piled wall. installation of tie rods and anchor piles. Forming, reinforcing and pouring of 200ft concrete bulkhead. Backfilling and compaction.

Calypso Marine Services Ltd, Chaguaramas Trinidad 2008 - 2009 Marine Consultant/ Contractor
Supply and installation of 180ft sheet piled concrete bulkhead and land reclamation

Cari-Dock (Clico) Chaguaramas Trinidad 2008 - 2009 Marine Consultant
Installation of 1 - 72" dia tubular pile (50 tons) and 5 - 56" dia piles for concrete dolphins for the stabilization of the dry dock.

Land Fish & Sea, Chaguaramas Trinidad 2008 - 2009 Contractor
Dredging and removal of approx. 1000 cubic yards of river stone from Dock frontage.

Petrotrin, Point-a-Pierre Trinidad 2008 - 2009 Marine Consultant
Installation of a 450ft sheet piled cofferdam, AZ-28 steel sheet piles. With Junior Sammy Co. Ltd (Bish Construction)

Industrial Transport Ltd, Brash Port, La Brea Trinidad 2008 - 2009 Marine Consultant/ Project Manager
Preliminary design of sheet piled bulkhead and breakwaters; dredge channel and turning basin; budget estimates, geotechnical investigation, bathymetric surveying and magnometer surveys for pipeline location. Coastal and environmental studies and surveys. Earth works, drainage and landscape design.

Christophe Harbour, KHT Holdings Ltd, ST. Kitts & Nevis 2008 - 2009 Marine Consultant
Sand depth investigation. Jet probing 25ft below sea bed at White House Bay, Ballast Bay and Turtle Bay.

Port Zante Marina, Urban Development Co. Ltd, St. Kitts & Nevis 2008 - 2009 Marine Consultant/ Contractor
Marine Rehab Project. Extracting and driving greenheart piles, steel tubalar pile driving. removal and rebuilding of wooden finger piers. Clam shell dredging, removal and disposing of 300ton concrete obstruction from the seabed.

Royal Caribbean Cruise Ship Company with Correia Construction, Roatan Honduras 2009 - 2010 Project Manager
Cruise ship Dock extension and improvements. Installation of 5 Breasting & Mooring Dolphins. 140ft dock extension. Pile driving of 55 - 24" dia steel piles @ 160ft long. Pouring offshore 1600 metric Tonnes of 5000psi concrete.

Tamarind Cove Marina, Nevis 2010 - 2011 Marine Consultant/ Project Manager
Preliminary designs, budget estimation and consulting. The proposed Marina development includes: Dredging, concrete bulkheads, concrete finger piers, wood dock and Armour Rock Jetties.

St. Vincent Government/ US Navy/ Coast Guard Building & New Dock Construction. Canouan 2011 - 2012 Project Manager/ Sub-contractor
Geotechnical Investigation, Bathymetric Surveying, Design and specifications. 165ft Concrete Dock construction, pile testing and pile driving

Christophe Harbour & Park Hyatt, Southeast Peninsular With Kelly Construction Ltd 2012 - 2017 Project Manager/Consultant/Contractor
Driving sheet, concrete , timber and tubular steel piles, rock augering, building of revetments and cofferdams.

Friars and Frigate Beach, St. Kitts. 2014 - 2015 Project Manager/Consultant
Dredging, Surveying, Profiling and Re-nourishment of the Beach.